Some roads will be shut over the course of eight weeks as vital gas main upgrades are set to start.
Gas network Cadnet will conduct vital work to keep gas flowing in Bushey, starting from January 25.
There will be phased closures in the area during the eight-week period as the group replaces old iron pipes with tougher plastic ones that should last at least 80 years.
Here is a list of the planned phased closures:
Phase 1 (January 25 to February 15)
Aldenham Road will be closed at the junction with The Avenue and Bushey Hall Road
Phase 2 (February 15 to March 1)
Four-way lights will be placed on the junction of Woodlands Road/ Bushey Grove Road.
Phase 3 (March 1 to March 29)
Aldenham Road will be closed at the junction with Belmont Road
Anyone with enquiries about the upcoming works are asked to contact Cadnet’s customer services team on 0800 389 8000.